What it does
You bring a project schedule: a Primavera P6 export (XER) or a set of CSV files. The tool plays the schedule out many times, a Monte Carlo simulation. Each time it draws every activity's duration within its range, applies the shared causes that move many activities together (drivers), lets each risk in the register happen or not according to its chance, and respects fixed dates such as possessions, blockades, ecological seasons and timetable changes. Costs follow the time, so a longer project pays its daily running costs for longer.
From those runs it shows:
- the chance of finishing by each date, and the confidence levels (P10 to P95) for the finish and the cost;
- when a finish can only fall on fixed dates, the chance of each of those dates;
- what drives the result: the drivers and activities that move the finish and the cost most;
- how often each activity is critical;
- a base and a scenario side by side, and the same model under three ways of linking the uncertainties.
Who it is for
Planners, project controls, cost and risk managers who model the schedule and cost risk of major projects, such as rail, road and other infrastructure, and who want to try a schedule risk analysis on their own schedules. The site is a test, open only to people the owner has invited.
What it shows: a worked example
These are real results from the engine that runs on this site, for its worked example: Ashbrook Vale Branch Line, a fictional 14 km electrified branch line with a viaduct, stations, signalling, consents, and a junction tie-in that can only happen in a Christmas blockade. Its numbers are illustrative. Every tester gets this project, and running it on the site with 200,000 iterations, seed 1 and chunk 134,000 gives exactly these figures.
Chance of finishing by the planned date
under 0.1%
the plan says 17 May 2032
Most likely completion date
13 Dec 2034
a chance of 73.4%
P80 outturn cost
£524.5m
against a planned £446.6m
5935d4862b40b126e30381695175b13ab0632f8e.When will it finish?
The plan finishes on 17 May 2032, and almost no run manages that. Entry into service can only happen at a timetable change. The completion date is lumpy, not smooth. It falls on a few fixed dates (windows or timetable changes), so the P-values jump from one of those dates to the next. The chance of each date is the better guide.
Table of the values
| Completion date | Chance |
|---|---|
| 17 May 2033 | 1.1% |
| 13 Dec 2033 | 19.4% |
| 17 May 2034 | 2.2% |
| 13 Dec 2034 | 73.4% |
| 13 Dec 2035 | 3.8% |
| other dates | 0.1% |
5935d4862b40b126e30381695175b13ab0632f8e.What will it cost?
Table of the values
| Level | Cost (GBP) |
|---|---|
| Plan | £446.6m |
| P10 | £495.1m |
| P50 | £514.8m |
| P80 | £524.5m |
| P90 | £530.7m |
| P95 | £538.4m |
5935d4862b40b126e30381695175b13ab0632f8e.What drives the finish?
The finish turns on whether activity J020, “Junction tie-in: Christmas blockade (9 days)”, is ready for its blockade. So the drivers and activities that move its ready date move the finish.
Table of the values
| Driver or activity | Rank correlation |
|---|---|
| Driver: Contractor productivity & labour availability | 0.44 |
| T210 Track installation km 3.5-7 | 0.41 |
| T110 Track installation km 0-3.5 | 0.38 |
| V030 Viaduct piers (8 no.) | 0.38 |
| Driver: Consents & statutory process | 0.37 |
| V010 Viaduct piling (rotary bored) | 0.37 |
| V060 Deck slab, parapets & waterproofing | 0.37 |
| V020 Viaduct pile caps & abutments | 0.36 |
5935d4862b40b126e30381695175b13ab0632f8e.Invite-only, and how your data is protected
- Invited testers only. Each tester has their own user name and password. Everything except this page and the privacy notice is behind the sign-in. Passwords are kept only in a scrambled form (bcrypt hashes), and an address that gets the password wrong 10 times in 10 minutes is blocked for an hour. There is no second sign-in step (no code by text or app).
- Your own folder. Each tester's projects and runs are kept in their own folder on the server. No tester can see another tester's data.
- Encrypted on the way. The site is always reached over an encrypted connection (HTTPS).
- Encrypted on the disk. All testers' data is kept inside an encrypted container on one server rented from Oracle in the UK (London). After every restart it is unlocked by hand, with a passphrase that is never stored on the server. Oracle's daily backups, each kept for 3 days, hold your projects and runs only in that encrypted form. The logins and the logs are kept outside the container, on the server's ordinary disk.
- What the encryption does not do. While the server is running, someone with full control of it, or Oracle's own systems, could read the data. A firewall, sign-in by key only for the server's administrators, and automatic security updates are the defence there. The owner, as the server's administrator, can read the data on the running server, and looks at it only to give support you ask for, or to delete data.
- Logs without content. The app's log holds no project content. The web server's log holds the time, address, user name, page and result of each request. Each line of either log is deleted from the live server within 14 days of being written, and is gone from the backups too within 17 days.
- Deleting. You can delete your runs, projects or all your data at any time, and it is gone at once; copies in the backups age out within 3 days. When the test ends, all testers' data is deleted within 30 days.
- Nothing else. This page has no trackers, no cookies, and nothing loaded from other sites. The app fetches nothing from the internet.
The privacy notice says what is held, where, why and for how long.
Request access
Send an e-mail to ask for a login. There is no form, and nothing you type is stored on this site.