Schedule and cost risk analysis, in your browser

How likely is each finish date, and each final cost? This tool answers that for a real project schedule, instead of giving one date and one cost.

What it does

You bring a project schedule: a Primavera P6 export (XER) or a set of CSV files. The tool plays the schedule out many times, a Monte Carlo simulation. Each time it draws every activity's duration within its range, applies the shared causes that move many activities together (drivers), lets each risk in the register happen or not according to its chance, and respects fixed dates such as possessions, blockades, ecological seasons and timetable changes. Costs follow the time, so a longer project pays its daily running costs for longer.

From those runs it shows:

Who it is for

Planners, project controls, cost and risk managers who model the schedule and cost risk of major projects, such as rail, road and other infrastructure, and who want to try a schedule risk analysis on their own schedules. The site is a test, open only to people the owner has invited.

What it shows: a worked example

These are real results from the engine that runs on this site, for its worked example: Ashbrook Vale Branch Line, a fictional 14 km electrified branch line with a viaduct, stations, signalling, consents, and a junction tie-in that can only happen in a Christmas blockade. Its numbers are illustrative. Every tester gets this project, and running it on the site with 200,000 iterations, seed 1 and chunk 134,000 gives exactly these figures.

Chance of finishing by the planned date

under 0.1%

the plan says 17 May 2032

Most likely completion date

13 Dec 2034

a chance of 73.4%

P80 outturn cost

£524.5m

against a planned £446.6m

The headline figures. Ashbrook Vale Branch Line, the worked example every tester gets: 200,000 iterations, seed 1, chunk 134,000, dependence off, engine commit 5935d4862b40b126e30381695175b13ab0632f8e.

When will it finish?

The plan finishes on 17 May 2032, and almost no run manages that. Entry into service can only happen at a timetable change. The completion date is lumpy, not smooth. It falls on a few fixed dates (windows or timetable changes), so the P-values jump from one of those dates to the next. The chance of each date is the better guide.

Chance of each completion dateColumns: the chance of each completion date. The plan's date, 17 May 2032, has a chance of under 0.1%. 17 May 2033 1.1%; 13 Dec 2033 19.4%; 17 May 2034 2.2%; 13 Dec 2034 73.4%; 13 Dec 2035 3.8%.0%20%40%60%80%17 May 2033: 1.1% chance1.1%17 May 203313 Dec 2033: 19.4% chance19.4%13 Dec 203317 May 2034: 2.2% chance2.2%17 May 203413 Dec 2034: 73.4% chance73.4%13 Dec 203413 Dec 2035: 3.8% chance3.8%13 Dec 2035
Table of the values
Completion dateChance
17 May 20331.1%
13 Dec 203319.4%
17 May 20342.2%
13 Dec 203473.4%
13 Dec 20353.8%
other dates0.1%
The chance of each completion date (dates with a chance under 0.1% each are in the table as other dates). Ashbrook Vale Branch Line, the worked example every tester gets: 200,000 iterations, seed 1, chunk 134,000, dependence off, engine commit 5935d4862b40b126e30381695175b13ab0632f8e.

What will it cost?

Outturn cost: the plan and the confidence levelsDots on one cost axis: Plan £446.6m; P10 £495.1m; P50 £514.8m; P80 £524.5m; P90 £530.7m; P95 £538.4m.£440m£460m£480m£500m£520m£540mPlan: £446.6m, the plan, with no uncertaintyPlan£446.6mP10: £495.1m, a 10% chance of costing this or lessP10£495.1mP50: £514.8m, a 50% chance of costing this or lessP50£514.8mP80: £524.5m, a 80% chance of costing this or lessP80£524.5mP90: £530.7m, a 90% chance of costing this or lessP90£530.7mP95: £538.4m, a 95% chance of costing this or lessP95£538.4m
Table of the values
LevelCost (GBP)
Plan£446.6m
P10£495.1m
P50£514.8m
P80£524.5m
P90£530.7m
P95£538.4m
The outturn cost: the plan, with no uncertainty, in grey, and the confidence levels in blue. P80 means an 80% chance that the cost is this or less. Ashbrook Vale Branch Line, the worked example every tester gets: 200,000 iterations, seed 1, chunk 134,000, dependence off, engine commit 5935d4862b40b126e30381695175b13ab0632f8e.

What drives the finish?

The finish turns on whether activity J020, “Junction tie-in: Christmas blockade (9 days)”, is ready for its blockade. So the drivers and activities that move its ready date move the finish.

What drives the scheduleBars: rank correlation of each item with the junction tie-in's ready date. Driver: Contractor productivity & labour availability 0.44; T210 Track installation km 3.5-7 0.41; T110 Track installation km 0-3.5 0.38; V030 Viaduct piers (8 no.) 0.38; Driver: Consents & statutory process 0.37; V010 Viaduct piling (rotary bored) 0.37; V060 Deck slab, parapets & waterproofing 0.37; V020 Viaduct pile caps & abutments 0.36.0.00.10.20.30.40.5Driver: Contractor productivity & labour availabilityDriver: Contractor productivity & labour availability: rank correlation 0.440.44T210 Track installation km 3.5-7T210 Track installation km 3.5-7: rank correlation 0.410.41T110 Track installation km 0-3.5T110 Track installation km 0-3.5: rank correlation 0.380.38V030 Viaduct piers (8 no.)V030 Viaduct piers (8 no.): rank correlation 0.380.38Driver: Consents & statutory processDriver: Consents & statutory process: rank correlation 0.370.37V010 Viaduct piling (rotary bored)V010 Viaduct piling (rotary bored): rank correlation 0.370.37V060 Deck slab, parapets & waterproofingV060 Deck slab, parapets & waterproofing: rank correlation 0.370.37V020 Viaduct pile caps & abutmentsV020 Viaduct pile caps & abutments: rank correlation 0.360.36
Table of the values
Driver or activityRank correlation
Driver: Contractor productivity & labour availability0.44
T210 Track installation km 3.5-70.41
T110 Track installation km 0-3.50.38
V030 Viaduct piers (8 no.)0.38
Driver: Consents & statutory process0.37
V010 Viaduct piling (rotary bored)0.37
V060 Deck slab, parapets & waterproofing0.37
V020 Viaduct pile caps & abutments0.36
Rank correlation with the tie-in's ready date, before it waits for its blockade: 1 means the two move in perfect step, 0 means no link. The eight strongest. The correlations are from the first 134,000 iterations, as the engine computes them. Ashbrook Vale Branch Line, the worked example every tester gets: 200,000 iterations, seed 1, chunk 134,000, dependence off, engine commit 5935d4862b40b126e30381695175b13ab0632f8e.

Invite-only, and how your data is protected

The privacy notice says what is held, where, why and for how long.

Request access

Send an e-mail to ask for a login. There is no form, and nothing you type is stored on this site.

Request access by e-mail